OEE calculator
Work out availability, performance, quality and OEE from one shift's planned time, downtime, ideal cycle time and part counts.
Result
Loading the calculator.
What OEE measures
Overall equipment effectiveness compares what a machine made with what it could have made in the time it was planned to run. It multiplies three losses together:
- Availability: time lost to stops. Run time ÷ planned production time.
- Performance: time lost to slow cycles and short stops. Ideal cycle time × total count ÷ run time.
- Quality: parts that were rejected or reworked. Good count ÷ total count.
OEE = availability × performance × quality. A machine that ran every planned minute, at its ideal cycle, with no rejects, scores 100%.
Getting honest numbers
- Leave planned breaks and scheduled maintenance out of planned production time.
- Use the fastest cycle the machine can hold for the ideal cycle time, not the average. A performance figure above 100% means the ideal cycle is set too slow.
- Count only parts that passed first time as good. Reworked parts count as rejects.
- Hand-written shift logs tend to miss short stops. Counting cycles and stops from the PLC gives a truer figure.